Since our last update, we have been able to plaster nearly half of the walls and complete nearly 100% of the multipurpose room! We’ve also placed the roof on half of the construction, and we are working on installing doors and windows. In the next two months, we plan to finish the roofing, install the plumbing, complete the kitchen, and finish the façade of the church.
The greatest issue has been that materials have been delayed in arriving, which has put off the progress of the work. However, we continue to move along steadily despite these challenges.
And we are expanding some of our evangelization practices into surrounding neighborhoods!